Two points in the public record that residents want the City to clarify. We set out what the documents say and what we are asking. We are not alleging that anyone has acted improperly.

1. The Section 37 agreement

What Council decided

What the land registry shows

The parcel register for PIN 21265-0317, printed November 1, 2026, lists the instruments registered on title, including the transfer to the current owners on September 25, 2025. It lists no Section 37 agreement among them. A register is a snapshot, and an agreement could be registered later. It is public through Ontario's land registry system.

Permits already issued

The City issued building permit 26 110316 BLD 00 BA on June 2, 2026 for standalone shoring and excavation. On October 8, 2026 it issued a revision (26 110316 BLD 01 BA) that adds tiebacks into the Ossington and Dupont right of way. Both describe the work as being for a future 17-storey mixed use building.

What we are asking

We ask the City to state publicly whether the Section 37 agreement has been executed and registered, and how the direction that no building permit be issued before then was applied to the shoring and excavation permit and its revision.

2. How tall is the building each filing describes?

What the records say

Descriptions of the project in City and Ministry records
RecordDateDescription
By-law 841-2022, Section 37 schedule and Diagram 72022A new 14-storey mixed use building, with a maximum height of 50.0 m, excluding the mechanical penthouse
Dewatering registration R-009-9199051442 (previous owner)March 22, 2023A new 14-storey mixed use building
Minor variance A0346/24TEY, Committee of Adjustment Notice of DecisionJune 11, 2024An increase from a 14-storey to a 17-storey mixed-use building, maximum height 56 m excluding the mechanical penthouse
Dewatering registration R-009-7398841836 (current owner)January 22, 2026A nineteen-storey high-rise residential structure
City building permit 26 110316 BLD 00 BA (standalone shoring and excavation)Issued June 2, 2026Shoring and excavation for remediation purposes for a future 17-storey mixed use building (the same number as the 2024 variance)
Site plan control resubmission 21 206371 STE 11 SASeptember 202619 storeys, residential with 116 m2 of commercial space
Revision 26 110316 BLD 01 BA to the shoring permitIssued October 8, 2026Adds tiebacks into the Ossington and Dupont right of way. Same description of a future 17-storey mixed use building

Sources: Ministry registration confirmations. By-law 841-2022. City of Toronto Building Application Status pages for 26 110316 BLD 00 BA (June 2, 2026) and 26 110316 BLD 01 BA (October 8, 2026). Applicant's resubmission documents.

How to read the differences

Ministry dewatering registrations are filed by the owner and are not planning approvals. A building permit is issued under the Building Code Act. Different filings serve different purposes, so some differences are not unusual. But the records describe the building as 14, 17 or 19 storeys depending on the filing, and the two most recent filings, the January 2026 registration and the current resubmission, say 19.

What we are asking

We ask the City to clarify two things: